Installation and Running of Heavy Material Decoiler
Installation of Heavy Material Decoiler:
1, the installation must be noted: the center of the material decoiler(both the length of the center of the blade) must be with the mold or punch or shearing machine in a center line.
2, the material of the current input frame for the three-phase 380V (420v / 220v) of the AC.
3, the control voltage within the electrical box for the single-phase 220V AC (provided by the machine transformer).
4, the induction voltage of 12V DC (provided by the machine transformer).
5, the length of the sensing time directly affect the operation of the material rack and life. The length of the sensing time is such that the average speed of the material frame will follow the requirements of the punching machine and the motor start is not too frequent. The factory setting is typically 3 seconds.
6, the material frame and leveling machine distance is generally about 3000mm, according to the characteristics of the material to decide.
7, the use of material before the frame must be clear that the specifications of the material, do not let the frame overload.
8, note that there is butter in the butter filling mouth.
9, often check the material on the side of the fasteners loose.