How To Set Up the Work After Selecting the Right Slitting Machine

How to debug the work after selecting the right slitting machine?

(1) check the mechanical and hydraulic connections of the slitting machine have not been loose, such as loose should be tightened in a timely manner.

(2) must be operated according to the requirements of each lubrication point to add lubricant

(3) to the oil tank into the work of the oil must be strictly filtered.

(4) After understanding the structure and principle of each part of the machine, the operator must be instructed by the installation personnel of the factory before proceeding to the next operation.

(5) Turn on the power and perform no-load test.

(6) Then you can start the motor, then you need to pay attention to observe whether the oil pump is stable in the process of operation, pay attention to whether there is no obvious noise, if not, you can carry out a test run.

(7) adjust the pressure of the system, so that the pressure value to maintain a stable state, in order to do a few shears sequence.

(8) the shear material flat on the worktable, adjust its shear length and angle, and then shear, after the cylinder stroke in place to keep pressure for 2-5 seconds, and then do a pressure test on the system, pay attention to the phenomenon of oil leakage, if there is, you must wait for the system to remove pressure after the exclusion.

Can do the above preparatory work in accordance with the order, for the extension of the machine life will be of great help, but also to ensure that each operating part can normally complete the operation.